Hi
1. I just installed latest version of dotProject, added some tasks which collectively take 5 days but noticed that the Summaries calculation (below all tasks for project) is saying "5 hours" not days 2. In "System Configuration" the Calendar Working Days was 1,2,3,4,5 but that showed as Tue to Sat when adding a task. Changed it to 0,1,2,3,4 which allowed Mon-Fri. Cheers Geoff |
|
#2
|
|||
|
|||
|
Ok, something odd going on here, with the calendar.
When I add a new task starting on the 9th April 2012 at 9am for 1 day and click "finish date" it sets the task to start on the 9th at 9am and finish on the 11th at 5pm (as there is a weekend inbetween) but thats still incorrect as that is two days not 1. ![]() |
|
#3
|
|||
|
|||
|
Ok, solved that by putting days back to 1,2,3,4,5 in the admin settings so now it is calculating the days correctly but displaying working week as Tue-Sat which I guess is just a miscalculation of the string in code.
|
![]() |